Cadence beats volume
Principals do not need fifty slides. They need a calendarised pack: progress vs baseline, cost vs contingency, open risks with owners, decisions required this month, and photo or evidence of critical packages.
Red flags
- Only percentages with no package map
- No change log
- Safety and quality as afterthoughts
- “All green” every month until a cliff
AHB stance
When we run delivery, the pack is part of the control model — not a marketing newsletter.